Plugging Wisconsin In
 
Home
About Us
Our Mission
Newsroom
Legislation
PSCW Proceedings
CFC Webcasts
Take Action
Contact Us
Related Links
Documents and Resources
Annual Conference

Electric Reliability and Competition White Paper

Transmission

Generation

Other Regulatory Reforms The Wisconsin Legislature passed Act 204 in 1998 to address electric shortage problems experienced in eastern Wisconsin during the summers of 1997 and 1998. Among other things, the Act required construction of 500 MW of new generation (including 50 MW of new renewable power resources), required identification of needed new transmission facilities, and streamlined the regulatory process. Act 204 was a first step to restoring the reliability of Wisconsin's electric system. However, further action by the Legislature and the Public Service Commission (PSC) is necessary to restore our position as a highly reliable, low-cost electricity state and to lay the foundation for increased competition in the electric industry for the benefit of all customers. We must restore customers' confidence in our state's ability to provide reliable power. By doing so, Wisconsin's thriving economy will continue to grow, with associated increases in jobs and income. These actions are designed to improve the long-term reliability of our electric system by encouraging the construction of new infrastructure. They are also intended to create greater elasticity of demand by providing market-based pricing opportunities for large customers.
TOP

TRANSMISSION

The Challenge. New transmission facilities can be very difficult to build if there is controversy over the environmental impacts of these facilities. Almost any new construction of high-voltage transmission facilities is likely to be opposed by some landowners and others in affected areas who are concerned about siting issues. Under existing law, there are few, if any, offsetting benefits for local communities from new lines. Also, transmission is inherently a regional, interstate function. Yet there are no regional regulatory arrangements in effect for oversight of the development of transmission projects in the upper Midwest. As a result, construction of new transmission desperately needed by Wisconsin to achieve a reliable electric system may be delayed substantially. To address these problems:

Recommended PSC action:

  • Implement promptly the recommendations in its Report to the Legislature dated September 1, 1998, that Wisconsin utilities build new transmission that will result in 3,000 MW of firm, simultaneous import capability from the west and the south. The new facilities should use existing rights-of-way wherever practicable and the routing and design should minimize environmental impacts consistent with achieving reasonable electric rates. The PSC should determine how the cost of these lines will be allocated among Wisconsin's transmission owners.

Recommended Legislative action:

  • Direct the PSC to condition the approval of construction of new high-voltage transmission projects that will materially increase import capability into Wisconsin on the owners reserving 50% of the new import capability for the benefit of a transparent, regional spot energy market that includes Wisconsin and for the possibility of retail competition in the future. This direction is necessary to ensure that current transmission owners and customers do not reserve all of the new capacity into the state on a long-term basis, frustrating the ability of retail customers to access competitive sources of energy if retail competition is authorized in the future. Until such time, this capacity will be available for short-term imports to lower the cost of electricity for all Wisconsin customers.

  • Require the PSC to adopt specific rules implementing the environmental standards of existing law. These rules should require preparation of environmental impact statements (EIS's) where appropriate, and adequate time to comment upon and be heard regarding such EIS's. The rules also should provide all parties with firm timetables so that environmental issues are dealt with appropriately, while dockets are processed without undue delay.
  • Create an incentive for siting of new high-voltage transmission facilities (230 kV and above) by imposing an impact fee on the owners of transmission facilities for which construction applications are filed in 1999, and thereafter, such that local governmental units through which new facilities are routed receive a payment comparable to the payment received for generating facilities located within the boundaries of such municipalities.
  • Create a one-time environmental impact fee to be paid by the owners of such new facilities, equal to a percentage (e.g., 5%) of the authorized original project cost to fund projects to "offset" environmental and aesthetic impacts of the transmission facilities. The fee would be paid to the counties and other units of local government through which a transmission facility is routed, with 50% going to the counties and 50% to the affected other local units (towns, villages and cities), allocated on the basis of the amount of investment in each county and local unit. These funds would primarily be used by the affected counties and local units for park, conservancy, wetland restoration and similar environmental offset projects, but may not be used by transmission applicants to finance the costs of specific mitigation measures for the project.
  • Authorize and request the Governor to negotiate and enter into a Regional Transmission Need and Siting Compact with one or more states in the upper Midwest to create a joint process to determine the need for and siting of regional transmission facilities that will be located in part in Wisconsin. The Compact should require compliance with each state's environmental and siting standards, but provide for a regional need determination and a mechanism to resolve siting conflicts between states.
  • Remove the sunset on the PSC's authority to order new transmission facilities set forth in Act 204.
TOP

GENERATION

The Challenge. Act 204 requires the construction of approximately 550 MW of new generation in eastern Wisconsin. This new generation may not be adequate to meet Wisconsin's needs, given anticipated delays in construction of new transmission, load growth, plant retirements and other factors. At the same time, if the needs of Wisconsin customers are not met by independent wholesale merchant plants, large utilities are reluctant to invest in ratebase generation due to uncertainty about future regulation. Also, landowners are concerned about siting issues. Therefore, additional actions need to be taken to encourage the responsible construction of new, efficient generation at appropriate sites and at the same time allow for the creation of a competitive generation market that will not be dominated by the incumbent investor-owned utilities.

Recommended PSC action:

  • Revoke its order establishing the two-stage CPCN process, so that utilities can proceed to propose new rate-based generation without going through that cumbersome process. Utilities will remain obligated under the federal Public Utility Regulatory Practices Act (PURPA) to purchase power from Qualified Facilities, and the siting process for new generation, including consideration of land-use and environmental impacts, will remain the same. Specific rules implementing the environmental standards of existing law should also encompass generation projects.

Recommended Legislative action:

  • Create additional incentives for local siting of new generation by imposing an impact fee on the owner of new generation, equal to the amount necessary to provide local governmental units where a new plant is located with the same amount of revenue each year for the life of the plant that they receive through the shared revenue account during the first year of service of the plant.
  • Where need may not be met by independent wholesale merchant plants, encourage the construction of new generation by utilities on a ratebase basis, by providing that the owner of a new ratebase plant will be entitled to elect when it receives its PSC construction authorization (CPCN) to commit to divest the new plant by auction if Wisconsin retail sales are deregulated, subject to PSC review of the fairness of the auction. If this election is made, the owner will be entitled to receive 20% of any profit above its net book value from the sale of such facility at auction, with 80% of such profit being flowed back to the ratepayers on the utility's distribution system. If the sale price at auction is less than net book value, utility shareholders will be required to absorb only 20% of the loss, with ratepayers being allocated the remaining 80% of the loss.
  • Enact the Customers First! public benefits package, with substantial funding for energy conservation in order to lower electric demand and with a proposed renewable portfolio requirement to increase the amount of renewable energy resources.
  • Clarify the authority of the PSC to order public utilities with an obligation to serve Wisconsin customers to construct new generation necessary for reliable service at appropriate sites. In addition, the law should be clarified to permit utilities that invest prudently in conservation projects in their service territories to recover their related investment and expenses in rates.
  • Direct the PSC and the DOA to encourage the development of high-efficiency, smaller-scale generating units that provide side benefits in the areas of support for the transmission and distribution system, power quality and environmental performance. These technologies include combined heat and power systems, fuel cells, microturbines and photovoltaic systems which can be situated in, on, or next to buildings or other load centers.
  • Direct the PSC to prepare, with the assistance of an expert economic consultant, a comprehensive report to the Legislature on the potential of generation market power to frustrate the creation of a competitive retail electricity market in Wisconsin and of measures that will eliminate this problem on a sustainable basis.
TOP

Other Regulatory Reforms

The Challenge. Many industrial customers have been upset by implementation of interruptible and curtailable programs during the last two summers. Many other customers have been displeased by urgent appeals to reduce consumption voluntarily. At the same time, retail customers have not received price signals at times of tight supply that could provide needed elasticity of demand. To address these issues:

Recommended PSC action:

  • Promptly authorize new retail real-time interruptible and curtailable programs for large customers that result in the customers receiving a market price signal for load reductions during peak periods when shortages may develop that could require curtailments of firm customers. For existing large customer firm load, the program should allow the customers to reduce verifiable load voluntarily on request in exchange for a payment based upon the market price for energy at the time of reduction. Existing interruptible/curtailable customers should be given an option to convert from current fixed credits to significantly lower fixed credits in exchange for receiving payments at the time of actual curtailments or interruptions based upon the market price of energy.
  • Expand performance-based ratemaking for investor-owned utilities based upon reliability, emissions and customer service performance. In addition, the PSC should provide for monetary credits to residential and commercial customers when an investor-owned utility is required by its own circumstances to issue an urgent appeal for voluntary conservation by such customers.
TOP

Recommended Legislative action:

  • Direct the PSC to develop and approve new market-based pricing options for customers that will allow them, through service from their existing utility, to take market risk for their energy purchases. The options should be designed to protect other customers from price swings.
  • Direct the PSC to issue a rule requiring full public disclosure by utilities of their current reliability status, including operating reserves, planning reserves, available transmission capacity into their systems and unit and line outage status. This disclosure will be necessary for customers to be able to respond to price signals and to prepare for possible shortages.